Q: The deadline for a specific project has not been properly communicated with stakeholders and is pushed out continuously. What type of project has this become?
or
Q: A certain project’s deadline has been constantly extended without adequate stakeholder communication. What kind of undertaking has this turned into?
- A deadline project
- An abandoned project
- A never-ending project
- A successful project
Explanation: The project mentioned, where the deadline has not been adequately stated and is repeatedly pushed out, might be deemed a “never-ending project” or a project with chronic delays. This indicates that there is a lack of clear communication, planning, or implementation, which has resulted in further delays in the completion date of the project.