As a Product Owner, you set the initial Sprint duration the team has to work on their items. This refers to what Scrum concept?

Q: As a Product Owner, you set the initial Sprint duration the team has to work on their items. This refers to what Scrum concept?

or

Q: You, as the product owner, choose how long the team will spend working on each item during the first sprint. To which Scrum principle is this related?

  • Interval
  • Timebox
  • Time frame
  • Schedule

Explanation: Within the framework of Scrum, the idea of “Sprint Planning” is connected to the act of “setting the initial Sprint duration as a Product Owner.” During the critical ceremony known as “Sprint Planning,” the Product Owner works in conjunction with the development team to determine the Sprint Goal and choose the Product Backlog items that will be worked on during the subsequent Sprint. During this planning session, the length of the Sprint that has been decided upon is also established. Iterations that are time-boxed are known as sprints, and they typically last anywhere from one to four weeks. The length of a sprint’s time frame is determined by many criteria, including the nature of the project, the capacity of the team, and the needs of the product.

Leave a Reply

Your email address will not be published. Required fields are marked *