What is a visual that measures time against the amount of work done and amount of work remaining on a project?

Q: What is a visual that measures time against the amount of work done and amount of work remaining on a project?

or

Q: What kind of graphic compares time to completed work and remaining work on a project?

  • Burndown chart
  • Data chart
  • Bar chart
  • A plan

Explanation: A “Burndown Chart” is a data visualization that compares the amount of time spent on a project to the quantity of work that has been completed and the amount of work that is still outstanding. In the field of project management, burndown charts are often used to provide a graphical depiction of the work that has been finished throughout the course of time as well as the work that is yet to be completed. In terms of performing activities and achieving project objectives within a certain amount of time, they assist project teams and stakeholders in tracking progress and identifying patterns.

Leave a Reply

Your email address will not be published. Required fields are marked *