Q: A project manager creates a task to have 100 books delivered to the company’s library. In the planning phase, how can the project manager account for the potential delays from the vendor?
- Communicate with the vendor daily.
- Split the delivery task into subtasks for the vendor.
- Limit the number of books delivered.
- Add a project buffer.