As a project manager assigned to a new project, what document can you reference in order to get information on past similar projects?

Q: As a project manager assigned to a new project, what document can you reference in order to get information on past similar projects?

or

Q: What document might a project manager assigned to a new project use to learn about previous, comparable projects?

  • The statement of work for the new project
  • The stakeholder feedback survey
  • The team members’ performance review
  • The project’s closeout report

Explanation: The closeout report contains a summary of the project, a list of the most important successes, a list of lessons learned, and other pertinent facts that might give significant insights into previous initiatives. It is a great resource that may be used to get an understanding of what aspects of the project were successful, what difficulties were encountered, and how improvements might be made in future initiatives.