Fill in the blank: The amount of work a Product Owner plans for the Sprint is based on________

Q: Fill in the blank: The amount of work a Product Owner plans for the Sprint is based on________

or

Q: Complete the blank: A Product Owner bases how much work to plan for the Sprint on ________.

  • direction from the customer
  • the future capacity of the team
  • direction from the stakeholders
  • the historical capacity of the team

Explanation: There is a correlation between the quantity of work that a Product Owner wants to do during a Sprint and the historical capability of the team.