Project Management Answers

You manage a project with multiple milestones dependent on each other. One team must hit these milestones before another team can begin their tasks. What type of chart can you use to track this project?

Q: You manage a project with multiple milestones dependent on each other. One team must hit these milestones before another team can begin their tasks. What type of chart can you use to track this project?

or

Q: You oversee a project with many interdependent milestones. Before another team may start working on their duties, one team has to reach these milestones. What kind of chart is suitable for monitoring this project?

  • Roadmap
  • Gantt chart
  • Burndown chart
  • Project status report

Explanation: Within the context of a project, a Gantt chart is a graphical depiction that depicts the timetable of the project across time. It displays the beginning and ending dates of many different aspects of the project, including tasks, milestones, and dependencies, among other things. When applied to the circumstances of your situation, a Gantt chart can efficiently depict the sequential nature of milestones as well as the connections between the work performed by various teams. Having this capability enables you to view the timeline of the whole project and get an understanding of how the milestones of one team may influence the beginning and end dates of the activities of the following teams.

Leave a Reply

Your email address will not be published. Required fields are marked *