Fill in the blank: When a team conducts Sprint Planning, they use the average velocity___________ of to determine how many items they can safely add to their Sprint Backlog.

Q: Fill in the blank: When a team conducts Sprint Planning, they use the average velocity___________ of to determine how many items they can safely add to their Sprint Backlog.

or

Q: Complete the blank: A team uses the average velocity___________ of to calculate the number of items they may safely add to their Sprint Backlog during Sprint Planning.

  • at least three story points
  • at least three days
  • at least three weeks
  • at least three Sprints

Explanation: In the process of Sprint Planning, a team will calculate the maximum number of items that they can add to their Sprint Backlog by calculating the average velocity of at least three completed Sprints.