Q: When creating milestones as a project manager, what should you avoid? Select all that apply.
or
Q: What should a project manager not do when setting milestones? Choose every option that pertains.
- Managing your milestones in one project management tool to stay organized
- Setting too many milestones because you want to appear ambitious to stakeholders
- Having no milestones because tasks are all you need to complete the project
- Using milestones as tasks because milestones should represent big moments in time and tasks are how to get there
Explanation: It is not something to avoid, but rather a smart practice, to handle milestones in a single project management platform to maintain organization. Additionally, it improves the structure of the project and makes it easier to communicate effectively with stakeholders.